The correct answer isDbecauseresidual riskis the remaining risk after controls and risk responses have been implemented, and it is the key measure used to determine whether the organization’s current level of risk is within its establishedrisk appetite. To assess whether risk has been appropriately managed, the organization must compare the remaining exposure, not the untreated exposure, against acceptable thresholds.
The other options are less appropriate:
A. Inherent riskrepresents risk before controls and therefore does not show whether risk has been appropriately managed.
B. Risk velocityindicates speed of impact, but not whether risk is within appetite.
C. Risk trendshows movement over time, but not the actual remaining exposure compared with appetite.
Exact Extracts supporting the answer:
“The most suitable output for justifying an information security program is considering residual risk in terms of acceptable risk.”
“The primary objective of a risk management program is to maintain residual risk at an acceptable level.”
“Residual risk is best reflected as risk remaining after the implementation of new or enhanced controls.”
“Acceptable risk for an enterprise is achieved when residual risk is within tolerance levels.”
“A successful risk management practice is indicated by minimizing residual risk.”
These extracts directly support thatresidual riskis the most useful information when comparing managed risk against established risk appetite.
===========