Question 1

Which of the following statements is true about open source software (OSS)?

Options:

A.

There is no risk involved when testing OSS.

B.

Modifications to OSS do not need to be tested.

C.

OSS can always be modified without significant repercussions.

D.

OSS can be problematic when it comes to keeping up with changes.

Buy Now
Question 2

Which of the following elements must be in place for a measure to be reliable?

Options:

A.

A well-designed data collection form

B.

An automated tool for calculating the measure

C.

An operational definition of the measure

D.

An online database for tracking the measure

Question 3

Which of the following sources of information would be most appropriate for a company to use to measure and monitor customer satisfaction?

Options:

A.

Comprehensive surveys covering all aspects of the customer experience

B.

Software quality’s attributes that have been classified as " critical " by key customers

C.

Feedback from customers regarding reliability data, especially concerning increases in the mean time to failure in the company’s products

D.

Market analysis reports that incorporate customer preferences when comparing the features of the company ' s products with those of its key competitors

Question 4

An environmental monitoring software system is required to measure ambient temperature and sound an alarm if the temperature drops below 19 3C or rises above 21 °C. Which of the following observed test results would be an error for this system?

Options:

A.

Temperature Display: 20 CC Alarm Status. Silent

B.

Temperature Display: Cannot measure Alarm Status: Silent

C.

Temperature Display: 15 °C Alarm Status Ringing

D.

Temperature Display: 21 °C Alarm Status Silent

Question 5

A project team conducts a review of its latest software design The review process is well-defined and is used by all projects within the company. As part of the review process, defect levels are compared against acceptable limits to determine appropriate corrective action. According to the CMMI-DEV Vl_2_. which of the following activities could the company perform to demonstrate characteristics unique to a Maturin ' Level 5 organization?

Options:

A.

Submit defect data to a team for future defect prevention.

B.

Collect defect data for each project ' s specific software process.

C.

Record defect data and establish the process capability baseline

D.

Assess the validity of each defect data measurement independently.

Question 6

Which of the following statements best describes the purpose of a matrix diagram?

Options:

A.

It allows a team to rank priorities and then quickly come to a consensus.

B.

It shows which problems offer the greatest potential for improvement.

C.

It allows a systematic comparison between sets of information.

D.

It shows the size of gaps between current and ideal performance areas.

Question 7

Which of the following documents must be under configuration control?

Options:

A.

Problem issues

B.

Control chains

C.

Test procedures

D.

Burn charts

Question 8

Defect prevention should be initiated during the

Options:

A.

test phase

B.

requirements phase

C.

design phase

D.

coding phase

Question 9

Which of the following organizational benefits is associated with increased satisfaction among external stakeholders?

Options:

A.

Improved predictability of costs

B.

Increased productivity of practitioners

C.

Strengthened ability to survive or prosper

D.

Reduced development and maintenance costs

Question 10

Regression testing can often be automated because this level of testing is performed

Options:

A.

late in the lifecycle when program structure documentation is available

B.

to assess coverage of all paths through the system

C.

many times with few changes

D.

at the end of product development when all system functionality is available

Question 11

Which of the following metrics would be most appropriate for evaluating how effective the peer review process was for removing defects?

Options:

A.

Cycle time

B.

Defect density

C.

First-pass yield

D.

Requirements volatility

Question 12

Which of the following categories describes acquirer-type stakeholders?

Options:

A.

Distributors: developers, suppliers

B.

Distributors, suppliers, users

C.

Indirect user, direct user, customers

D.

Indirect user, direct user, distributor

Question 13

During concurrent development., a user reported a problem with Version 1 of the software product. A software quality engineer determined the problem originated m Version 2 of the product. Which of the following actions would be most appropriate for the software quality engineer to take first to fix the problem?

Options:

A.

Merge the fix into Version 3.

B.

Branch the Version 2 codeline

C.

Add new functionality to Version 2.

D.

Label Version 2 as part of Version 1

Question 14

What type of questions should developers ask customers when discussing requirements at the inception of the project?

Options:

A.

context-free

B.

detail-driven

C.

multiple-choice

D.

yes/no

Question 15

One advantage of using the pair programming development methodology is that

Options:

A.

fewer defects are introduced into the code

B.

fewer unplanned features are identified

C.

more collaboration occurs with the customer

D.

more work is devoted to completing the documentation

Question 16

Which of the following lifecycle models is designed to mitigate risks during development?

Options:

A.

Incremental

B.

Spiral

C.

Waterfall

D.

Rapid application development

Question 17

During an in-process audit of a development team, a software auditor discovers that a step is missing in the development process being used by the team. The absence of this step, which is not in the approved software development procedures and standards, has the potential for causing a product failure. Which of the following would be the most appropriate course of action for the auditor?

Options:

A.

Do not include the finding in the audit report since the step is not part of approved procedures.

B.

Immediately request that management approve an addition to the procedures so the finding can be included in the audit report.

C.

Include the finding in the audit report since part of the job of an auditor is to evaluate processes.

D.

File a finding separately from the audit report so that it will be included in the next audit of the development group.

Question 18

Which of the following steps comes first during release planning for waterfall-type projects?

Options:

A.

Define the scope of the software being developed.

B.

Determine which problems will be corrected in the next release.

C.

Select the set of requirements that will be included in the release.

D.

Confirm the implemented software meets the specified requirements.

Question 19

Which of the following actions will have the greatest impact on defect removal efficiencies?

Options:

A.

Avoiding style issues during reviews

B.

Holding inspections of requirements and design

C.

Conducting formal testing by trained specialists

D.

Performing code inspections

Question 20

As a side job: a trio of software quality ' engineers developed a database management system for XYZ, a non-competing company and subsequently packaged it for commercial sale as DBM Solutions. The engineers supervisor read about the new system in a trade magazine and asked the engineers for their opinion on whether to buy DBM Solutions. What would be the most appropriate way for the engineers to respond to this situation?

Options:

A.

Explain their role in developing the software and ask to be excused from participating in the purchase decision.

B.

Advise XYZ about their company ' s interest in the software and ask XYZ to make a presentation of the software

C.

Advise their supervisor to buy the software., based on the fact that the product will meet the company ' s requirements.

D.

Offer to examine the software, evaluate it with respect to the company’s requirements, and report on the findings

Question 21

Which of the following sources is most likely to contain the information needed to propose a software correction?

Options:

A.

Physical configuration audit report

B.

Requirements traceability matrix

C.

Customer satisfaction survey

D.

Software problem report

Question 22

The benefits of having the data owner collect the data is that data owners

Options:

A.

can process data as it is being created, which increases collection speed

B.

know which are the best statistical tools and techniques for data analysis

C.

have in-depth knowledge of the data: therefore, the data they collect will be bias-free

D.

are more likely to detect anomalies in the data as it is being collected., which helps increase accuracy

Question 23

During the requirements planning stage, management ' s responsibility is to

Options:

A.

provide effort estimates for implementation

B.

ensure that appropriate stakeholders are involved

C.

confirm customer requirements

D.

define the quality criteria for the project

Question 24

Results from a process audit show that the requirements group does not control changes to its software specifications. Which of the following basic requirements should be added to the software configuration management (SCM) policy?

Options:

A.

SCM must be implemented throughout the project ' s lifecycle.

B.

SCM must be implemented for externally deliverable software products

C.

Responsibility- for SCM must be explicitly assigned for each project

D.

Each project must have an established repository for storing configuration items.

Question 25

A cross-functional team has been established to improve the effectiveness of the inspection process. All team members have volunteered to participate and are experienced in the current process. In this situation, the team sponsor ' s role should be to

Options:

A.

provide die team with specific instructions and closely supervise its performance

B.

explain each step before the team can take action

C.

participate in team meetings and facilitate daily decision-making

D.

authorize the team to make decisions and implement changes

Question 26

In a software development company, which of the following authorities is responsible for establishing the company ' s quality policies?

Options:

A.

Senior management

B.

Quality management

C.

Engineering development teams

D.

A cross-functional ream of developers and managers

Question 27

The following chart was developed to compare defects in two projects. Which of the following conclusions can be drawn from this chart?

Options:

A.

The projects have the same defect rates.

B.

The projects have different defect profiles.

C.

More defects were removed per phase from Project 1 than Project 2.

D.

More defects were removed per phase from Project 2 than Project 1.

Question 28

Which of the following statements from a software requirements document is an example of a functional requirement?

Options:

A.

“The system must reject non-numeric input.”

B.

“The system must be 99.9% operational.”

C.

“The system’s response time must be less than three seconds.”

D.

“The system must be developed according to IEEE standards.”

Question 29

The primary reason that software development organizations need to consider privacy issues related to their products is that

Options:

A.

different cultures have varying degrees of sensitivity toward privacy

B.

many databases contain personal information that can be put at risk

C.

software design documents are classified as proprietary information

D.

security protocols are difficult to test

Question 30

An effective listener is defined as someone who

Options:

A.

forms a reply while the speaker is talking

B.

is attuned to nonverbal cues

C.

asserts opinions without fear

D.

draws parallels to other situations or times

Question 31

Which of the following is most often the focus of testing in an organization with a mature testing strategy?

Options:

A.

Complete testing to identify product defects

B.

Functional testing to prove a product is correct

C.

Testing the products throughout the development cycle

D.

Extensive strategic beta testing with a selected group of customers

Question 32

A static analysis tool is used to

Options:

A.

ensure that the system meets customer expectations

B.

identify potential problems

C.

trace test cases

D.

improve the time to market

Question 33

During what activity would it be appropriate for a team to use a complexity analyzer0

Options:

A.

Requirements analysis

B.

Requirements traceability

C.

Test planning

D.

Test execution

Question 34

Which of the following aspects of information systems is disaster recovery primarily concerned with protecting?

Options:

A.

Integrity

B.

Availability

C.

Authorization

D.

Confidentiality

Question 35

Which of the following as the most appropriate source of metrics that support the change management decision-making process?

Options:

A.

Software library

B.

Software compiler

C.

Status accounting tool

D.

Version control system

Question 36

Which of the following documents is examined in a high-level architectural design review?

Options:

A.

Acceptance test plans

B.

Detailed software designs

C.

External interface specifications

D.

Software requirements specifications

Question 37

Which of the following activities would be most appropriate for mitigating the risk of releasing patches to software?

Options:

A.

Partial releases

B.

Software rebuilds

C.

Regression testing

D.

Configuration management

Question 38

Which of the following statements describes the output from a code coverage monitor?

Options:

A.

Calculated values are documented, including where the calculations were made.

B.

Data types are manipulated by the correct modules.

C.

Lines of code are executed in the correct order.

D.

Lines of code and branches or paths have been executed.

Question 39

Which of the following actions is designed to prevent future defects?

Options:

A.

Using white-box testing

B.

Applying reverse-engineering to a defective system

C.

Conducting a causal analysis

D.

Injecting defects to test a system

Question 40

Which of the following software security requirements objectives is met by limiting access to the system through passwords?

Options:

A.

Supplying an audit trail

B.

Preserving data integrity

C.

Maintaining access control

D.

Providing backup and/or recovery

Question 41

Which of the following best defines the total cost of quality for a software project?

Options:

A.

Quality assurance and testing budgets

B.

Fixing defects and maintenance

C.

Prevention, appraisal, and failures

D.

Planning, designing, and testing

Question 42

A strong customer feedback management process primarily helps an organization improve

Options:

A.

profitability

B.

existing products

C.

company stock price

D.

software development time

Question 43

Which of the following steps is taken first when managing earned value metrics?

Options:

A.

Determining the critical resources to be tracked

B.

Calculating the planned value, earned value, and actual value metrics

C.

Analyzing the earned value metric compared to the other metrics to date

D.

Allocating the resource budget to individual tasks in the work breakdown structure

Question 44

Which of the following benefits is associated with using the iterative model?

Options:

A.

It can be tailored to the needs of the project and organization.

B.

It does not require knowledge of all the requirements up front.

C.

It correlates directly to the deliverables of software development.

D.

It focuses on exploring options early by feedback through prototyping

Question 45

According to the ISO 9001 standard, who is responsible for ensuring the effectiveness of a quality management system?

Options:

A.

Executive management

B.

The quality director

C.

The project manager

D.

Software quality engineering

Question 46

Which of the following inputs is used in software cost estimation models?

Options:

A.

Lines of code

B.

Number of users

C.

Age of the software

D.

Maintenance requirements

Question 47

Which of the following examples is the most appropriate product-level attribute template for a system determined to be safety-critical software?

Options:

A.

The system shall react to < type of accident or hazardous condition > by performing < type of action! s) >

B.

The system shall < time out, log out. lock > access to < data, asset, function > after < defined time period > of inactivity

C.

< quantity > of user < error type > mistakes made by a < user type or role > per < time unit > under < defined conditions >

D.

< mean time or average time > for a < defined product or component > to experience < defined failure type > under < defined conditions >

Question 48

Which of the following activities is part of performing verification and validation on safety-critical features at even ' step of the life cycle?

Options:

A.

Identifying and mitigating security risks to prevent safety and hazard risks

B.

Documenting software safer. ' risk plans that include rigorous development processes

C.

Performing software hazard analysis and determining acceptable levels of safety risks

D.

Providing mechanisms for discovering, correcting, and preventing the recurrence of safety’ risks

Question 49

Maintenance activities are commonly characterized as

Options:

A.

technological

B.

definitive

C.

corrective

D.

predictive

Question 50

In order to reduce inconvenience for customers during a maintenance phase, support staff should concentrate on fixing

Options:

A.

all known defects

B.

minor defects only

C.

defects that affect the “vital few” customers

D.

defects that impact essential operations

Question 51

When a defect is discovered during the test phase., what is the earliest phase in the software lifecycle that could need rework to resolve the defect?

Options:

A.

Implementation

B.

test

C.

requirements

D.

design

Question 52

A requirements change impact analysis should be performed when

Options:

A.

configuration items are placed under formal change control

B.

configuration items are marked as baselined

C.

a change has been approved by the change control board (CCB)

D.

a change is being reviewed by the change control board (CCB)

Question 53

Under which of the following major Cost of Quality categories would testing a software upgrade be classified?

Options:

A.

Appraisal

B.

Prevention

C.

Internal failure

D.

External failure

Question 54

What type of technology- is designed to provide organizational partners with real-time access to information on a business-to-business architecture?

Options:

A.

Embedded system

B.

Encrypted email

C.

Extranet

D.

Internet

Question 55

Which of the following formulas should a reviewer use to calculate defect yield for a single review?

Options:

A.

100 × defects removed before compile ÷ defects injected before compile

B.

Defects per hour in Phase 1 ÷ defects per hour in unit testing

C.

100 × compile time × test time ÷ total development time

D.

100 × design review time plus code review time ÷ total development time

Question 56

Globalization requirements involve

Options:

A.

defining the required information flow across shared interfaces to external entities

B.

defining problems to be solved or opportunities to be addressed by the software product

C.

looking at the capability of the software product from the perspectives of various stakeholders

D.

developing software that can be adapted to target markets and customizing software for those markets

Question 57

If (X < Y and Z = 3)

Then do segment A

Set W = 3

The following test cases are used to test the above code:

Test Case 1: X < Y and Z = 3

(Do Segment A, then set W to 3)

Test Case 2: X < Y and Z ≠ 3

(Do not do Segment A, then set W to 3)

Test Case 3: X = Y and Z = 3

(Do not do Segment A, then set W to 3)

Test Case 4: X = Y and Z ≠ 3

(Do not do Segment A, then set W to 3)

For which of the following types of test coverage would all four of the test cases shown above need to be executed?

Options:

A.

Condition

B.

Branch

C.

Line

D.

Complete

Question 58

Who is responsible for walking through business scenarios to determine the completeness of the defined requirements?

Options:

A.

The analyst

B.

The tester

C.

The quality function representative

D.

The product developer

Question 59

Which of the following testing methods is used to identify “dead code”?

Options:

A.

Black-box

B.

Simulation

C.

White-box

D.

Regression

Question 60

An organization uses the plan-do-check-act (PDCA) cycle to align its processes to an international quality standard, which of the following activities would be performed during the " act " step?

Options:

A.

Identifying actions to be performed during the pilot

B.

Performing internal audits of the system

C.

Making quality system revisions

D.

Documenting the problems to present to management

Question 61

A function point analysis uses counts of which of the following elements^

Options:

A.

Data definitions

B.

Physical lines

C.

Executable lines

D.

External inquiries

Question 62

In lean software development extra features should be identified as

Options:

A.

potential re-use elements

B.

an internal cost of quality

C.

defects

D.

waste

Question 63

Which of the following types of testing is conducted to test the interfaces and interactions between source code modules?

Options:

A.

system

B.

integration

C.

functional

D.

component

Question 64

A software developer is replacing a higher level code with a test code that establishes a function and passes test data to that function What type of test environment is the developer using

Options:

A.

Regression

B.

Static

C.

Driver

D.

Stub

Question 65

Which of the following factors is important in a software product m terms of its adaptability?

Options:

A.

Efficiency

B.

Accessibility

C.

Trainability

D.

Portability

Question 66

A test team is tasked to test an application that creates a large volume of reports. During regression testing, which of the following tools should the team use to assure that the application continues to produce the appropriate reports?

Options:

A.

A file format conversion tool

B.

A file comparison tool

C.

A string finding tool

D.

A keyboard capture and replay tool

Question 67

Each software development process should have a clearly defined set of inputs, activities, outputs, and

Options:

A.

stimuli criteria

B.

entry exit criteria

C.

go no-go criteria

D.

cost estimates

Question 68

Which of the following details should be included in a software configuration management plan?

Options:

A.

Potential changes to identified configuration items

B.

Configuration control board level of authority

C.

Programming language used for coding

D.

Software integration test baselines

Question 69

Which of the following organizational objectives is met through monitoring of software metrics?

Options:

A.

Ensuring programs work properly

B.

Improving processes and products

C.

Limiting the number of deviations

D.

Measuring the level of development effort

Question 70

Which of the following roles acts as the final arbitrator for any audit-related issues that cannot be handled at a lower level?

Options:

A.

The client

B.

The auditee

C.

Lead auditor

D.

Auditee management

Question 71

Which of the following skills is a component of active listening?

Options:

A.

Formulating questions

B.

Planning a response

C.

Taking notes

D.

Paraphrasing the speaker

Question 72

As it relates to testing, the phrase " 80% coverage " means 80% of the

Options:

A.

software is error-free

B.

statements in the program have been tested

C.

planned test cases have been completed

D.

predicted errors have been uncovered

Question 73

A software quality engineer (SQE > is testing software in a system used to monitor critically ill patients and administer dosages of life-sustaining medicines Tests reveal a flaw that could result in an unscheduled shutdown under certain circumstances. Ox er the SQE ' s verbal and written objections: the director of engineering decides to ship the system. The SQE knows from experience that " whistle-blowers " in the company have lost their jobs The most appropriate next step for the SQE would be to

Options:

A.

gam support from workers

B.

inform the customer

C.

discuss with top management

D.

remain silent

Question 74

When modifications are made to a software system, which of the following tools is helpful for determining appropriate verification and validation tasks?

Options:

A.

Affinity diagram

B.

Pareto chart

C.

Cause and effect diagram

D.

Requirements traceability matrix

Question 75

Which of the following tests is most appropriate for efficiently determining if the software handles time zones correctly?

Options:

A.

Fault insertion

B.

Boundary value

C.

Fault-error handling

D.

Equivalence class partitioning

Question 76

An effective team facilitator should have which of the following characteristics?

Options:

A.

Neutrality

B.

Decision-making ability

C.

Technical expertise

D.

Competitiveness

Question 77

Which of the following types of test coverage is most appropriate when the objective is to determine if the software has any problems handling all the required possible hardware and software designs?

Options:

A.

State

B.

Interface

C.

Data domain

D.

Platform configuration

Question 78

Which of the following problem-solving tools is most appropriate for breaking down ideas into progressively greater detail?

Options:

A.

Tree diagram

B.

Matrix diagram

C.

Affinity diagram

D.

Relationship diagram

Question 79

The following chart was created by a team.

The chart shows number of defects over time, including projected unit test defects, projected integration test defects, actual unit test defects, and actual integration test defects. Which of the following conclusions can be drawn from this chart?

Options:

A.

Unit testing has been poorly planned.

B.

Unit testing is isolating as many defects as predicted.

C.

Integration testing is very effective in isolating defects.

D.

Integration testing is isolating as many defects as predicted.

Question 80

In the archival process, retention of historical records is

Options:

A.

not required

B.

set for at least 2 years

C.

needed for all documents

D.

specified by the organization

Question 81

Which of the following corrective actions is the first action to take when a project experiences a significant deviation on baselined budgets, baselined schedules, or required quality levels?

Options:

A.

Add resources and continue with the plan.

B.

Cancel the project because of the deviation.

C.

Create a new baseline and continue with the plan.

D.

Realign project actuals and continue with the plan.

Question 82

When a team is defining a software metrics program, which of the following steps must be taken first?

Options:

A.

Determine what data to collect.

B.

Collect preliminary data

C.

Establish the data collection goal.

D.

Select the metrics to report

Question 83

Which of the following is a defect prevention activity?

Options:

A.

Internal audit

B.

External audit

C.

Training

D.

Root cause analysis

Question 84

The severity of a failure in a software operation is determined by the

Options:

A.

estimated cost to find the fault and deploy a fix

B.

impact on the customers

C.

number of customers reporting the failure

D.

amount of time the software has operated without exhibiting the failure